---++ Project Budget Approval Use Solomon->Project Budgeting->Budget Review & Approval. "View Detail" gives the Budget Inquiry and Analysis screen. Then use Solomon->Project Controller->Project Maintenance to: * Untick "resource assignment required to charge tasks". * Tick "Available for all employees to change" * Set project from Plan to Active (In Status Flags at the bottom left of the window) -- Main.TonyFarrell - 05 Apr 2007